Works at the Pauline Griffin Building

On Monday 11 September, the contractors will commence with site establishment at the Pauline Griffin Building. The early works will include the installation of temporary fencing, establishment of site sheds and traffic management around the site. After the site has been established, removal of the hazardous material will start, followed by the demolition of the Pauline Griffin Building.

The duration of the early works activities is approximately eight weeks. There will not be any changes to road conditions or adjacent building access during this early works phase.

More information about the development of a new facility for the ANU College of Arts and Social Sciences can be found on the Campus development page.