CMS Project Schedule reset

28 June 2018

Following an unexpected delay in the availability of the CMS Release 3 (R3) functionality and approval from the Project Steering Committee, the CMS Project has reset all R3-related and GO-LIVE-related activities and milestones.  In replanning the remainder of the project, the following Key Milestones have been set:

MS#

MS Name

Revised Date

Status

1

R2 UAT Complete

5-Jun-18

COMPLETED

2

R3 UAT Commence

16-Jul-18

ON TRACK

3

Production Data Migrated (for UAT)

31-Aug-18

PLANNED

4

Planned Version Upgrade

08-Oct-18

PLANNED

5

R3 UAT Complete

19-Oct-18

PLANNED

6

UICT CAB

23-Oct-18

PLANNED

7

CMS ‘Go / No-Go’

25-Oct-18

PLANNED

8

CMS Deployed

26-Oct-18

PLANNED

9

CMS GO-LIVE

31-Oct-18

PLANNED

10

CMS Project Closed

16-Nov-18

PLANNED